Alerts
MME defines schedule of Energy Auctions until 2024
It was published on December 20th of 2021 edition of Union Official Journal the Ordinance Acts no. 32/GM/MME and no. 33/GM/MME, defining, respectively, the estimated schedule of auctions of power generation and power transmission until 2024.
Among energy auctions, reserve of energy and reserve of power auctions, and supply of isolated systems auctions, the Ordinance Act no. 32 foresees eight auctions of power generation in 2022, seven in 2023 and other seven in 2024, with the following characteristics:
2022 | 2023 | 2024 | |
New Energy | A-4 in May
A-5 e A-6 in August |
A-5 e A-6 in August | A-5 e A-6 in August |
Existing Energy | A-1 e A-2 in December | A-1 e A-2 in December | A-1 e A-2 in December |
Supply of Isolated Systems | In October | In October | In October |
Reserve of Energy Capacity | In September | In March | In March |
Reserve of Power Capacity | In November | In November | In November |
Regarding to power transmission, the Ordinance Act no. 33 defines the doing of two auctions per year, the first in June and the second in December. The deadline to celebration of Transmission System Use Agreement (“CUST”) of each auction follows the table at Attachment I of the Ordinance, as described below:
Auction | Public Session | Deadline to celebrate CUST |
1st of 2022 | June/2022 | January 31st of 2022 |
2nd of 2022 | December/2022 | June 15th of 2022 |
1st of 2023 | June/2023 | January 13rd of 2023 |
2nd of 2023 | December/2023 | June 13rd of 2023 |
1st of 2024 | June/2024 | January 15th of 2024 |
2nd of 2024 | December/2024 | June 15th of 2024 |
Lefosse Energy Team is closely monitoring the legal and regulatory changes in Brazilian Electrical Sector, and is at disposal of all market players to advise in relevant themes of this Sector.